Friday, October 13, 2006
Fairfax Creek Restoration / Flood mitigation at 300 Olema
We are excited to report that this project began yesterday, according to our Public Works Director, Debra Sue Johnson. Work has started on the natural creek section of the project. We are still working on the design modifications to decrease costs in the concrete channel section since this area will need additional structural analysis for the bridge work. This project will widen the culvert and allow a greater flow capacity, restore the natural creek bank, and alleviate the flooding risk in this area. The bids came in quite high on this project, but thanks to Debra Sue, she has been able to negotiate and modify the project to complete the major work within our budget.